Mike Sawyer, the new Transportation Engineer for the City of Richmond, and 5th District Councilman, Parker Agelasto, provided the following construction schedule update for the Idlewood Roundabout to the RNA (Randolph Neighborhood Association) on May 1, 2015:
Right of Way Completion, June 2015
Plan Completion, July 2015
Bid Advertisement, August 2015
Award Contract, October 2015
Start Construction, November 2015
Complete Construction, March 2016Michael B. Sawyer, PE